The planning schedule is important because a study involves several participants, and this may cause the schedule to slip at any of the validation steps.
Read moreWe have observed that the planning phase is too often shortened to the detriment of the questionnaire, which is nonetheless definitive.
Actions | Working days |
---|---|
Project go-ahead | D |
Launch meeting | D+5 |
Questionnaire proposal | D+7 |
Questionnaire validation | D+8 |
Questionnaire programming | D+9 to D+10 |
Validation of test link | D+11 |
Field launch | D+12 |
End of field | D+19 |
Data processing | D+19 to D+23 |
Analysis repports | D+24 to D+30 |
RPresentation of repport | D+30 |
Oral presentation | Specify |
Count on an extra week for your side during a project because internal validation
will always take longer than planned!